Podensac (33)
USLD and EHPAD
PROJECT OWNER
Nursing home
PROGRAM
Reconstruction of 202 beds: partial restructuring and upgrading of 77 beds
BET
BETOM INGENIERIE, BETR, CAP TERRE, DEBARRE, DUPLANTIER, ORFEA
surface
12 746 m²
AMOUNT OF WORK
18.41 M€ H.T
ASSOCIATE ARCHITECT
ASSOCIATE ARCHITECT
PROJECT MANAGEMENT ASSISTANT
SEM 47
MISSION
Complete project management
SELECTION MODE
Competition
PRODUCTION
Delivered in November 2023
PHOTOGRAPHER
L'Atelier Caumes
The Podensac hospital, made up of a group of heterogeneous buildings, launched an architectural competition to rebuild its site, in a "drawer" operation, by demolishing/reconstructing existing buildings to obtain, in fine, a coherent architectural and functional object. This phased operation, on an occupied site, will take 48 months to complete.
As the only long-term care center in the area, the project is a vital link in the geriatric care chain. The new care center is intended to give the site a new coherence and face, through a combination of solid elements (buildings) and empty elements (gardens, patio).
The architectural layout of the project takes into account the presence of an existing building, which we are restructuring and bringing up to standard. By integrating the existing building, our layout aims to create a coherent overall image of the residence as a single establishment, rather than a motley collection of buildings.
In situ reconstruction of a long-term care unit and a 279-bed EHPAD nursing home
Reconstruction of 202 beds in a 279-bed facility and restructuring of 77 EHPAD beds
- 14 UHR beds,
- 36 USLD beds,
- 152 EHPAD beds divided into 4 units of 38 beds each,
- 14 PASA places,
- 6 day care places,
- 1 production kitchen and 1 set of logistics premises.